I-80 Westbound Closure for Bridge Work

ne-department-of-transporat

Aug. 28, 2024 (Lincoln, Neb.) — Weather permitting on Monday evening, Sept. 9, the westbound

lanes of I-80 will be closed at 8 p.m., according to the Nebraska Department of Transportation.

Hawkins Construction, Co. of Omaha is the contractor for the project. Westbound I-80 traffic will be

detoured at the I-80 / I-180 Interchange (Exit 401) and routed west on Hwy 34 to Matzke Highway,

turning south and accessing I-80 at the Milford Interchange (Exit 382).

Detours will be removed and I-80 traffic will resume by 6 a.m. on Tuesday, Sept. 10. The closure

is for the placement of bridge girders over I-80 on the NW 126th Street and NW 98th Street overhead

bridges. In the event of inclement weather conditions, this schedule will be revised.

Motorists are reminded to drive cautiously in and near work zones, to buckle up, put phones down.